King Fahd International
Airport
|
General Parameters
- Annual 11,6 Million
- Average day of peak month 38,150
- Peak hour arrivals (ADPM)
a. Domestic 850
b. International 1,220
- Peak hour departures (ADPM)
a. Domestic 1,020
b. International 1,330
- total 15,800
- Peak Shif5t 7,150
- Total 4,265 Hectares
- Airport 3,675 Hectares
- Construction Support/Utility Plants 510 Hectares
- Community 80 Hectares
- Maximum (Summer) 52 c 125 F
- Maximum (Summer) -2 C 28 F
- Maximum Speed 87 km/h
- Gusts 122 km/h
- Prevailing direction North-Northeast
Site Development
- Graded Areas 1,630 Ha
- Excavation 10 million m3
- Embankment 12 million m3
- Open lined channels 30,500 m
- Pipe culverts (1.0 to 1.5 m 0) 8,700 m
- Bix culverts (4 m x 2 m) 2,500 m
- Storm drains 7.600 m
(Note: See also utility systems for power cable
water lines and sewer lines
Airfield facilities
- 7.5m paved shoulders 120m paved blast pads
Taxiways (AC)
- West taxiway 10,000m x 23/2/m
- 11m paved shoulder
- East taxiway 6,600m x 23/2/m
- 11m paved shoulder
- North cross taxiway 1,500m x 30m
- 12 m paved shoulder
- West terminal 426,000m2
- Royal terminal 124,000 m2
- General aviation 180,000 m2
- West air cargo 55,000 m2
- East & West Security 2 x 7,000 m2
- Compass calibration pad 12,000 m2
- West terminal contact gates 400 Hz power
- Preconditioned air,
- fuel hydrants
- West terminal remote gates Fuel hydrants 60Hz Power
- Royal terminal contact gates 400 Hz power
- Preconditioned air
- Aircraft docking.
- Royal terminal ceremonial gate Preconditioned air
- 60 Hz power
- Cargo terminal loading docks 400 Hz power
- Aircraft docking
- (East & West runways, taxiways & Apron) Airfield Lighting
- Airfield Markings
- Taxiways guidance signs
- Precision approach
- Path indicator (PAP 1)
Roads & Bridges
- North access road (Freeway) 115 Km/Hr
- Rind & community access road 80 Km/Hr
- (Expressways)
- Service & secondary access roads 50 Km/Hr
- Air side service and emergency roads 30 - 80 Km/Hr
- (Local)
- 6 Lanes 5.6 Km/Hr
- 2 Lanes 7.7 Km/Hr
- 4 Lanes 5.4 Km/Hr
- 2 Lanes 303 Km/Hr
- 3 Lanes 1.5 Km/Hr
- 4 Lanes 15.0 Km
- 2 Lanes 3.2 Km
- 4 x12.3m Wide x 55.22m
- 2 x 80 m Wide x 57 m
UTILITY SYSTEMS
Sized for planning years 1995 and 2005
- a. Passenger 38,100 persons/day
- b. Visitors 11,000 persons/day
- c. Employees 13,600 persons/day
- d. Residents in camps 4,000 persons
- a. Power
- i. Commercial 47,400 kW
- ii Standby 16,100 KW.
- b. water 11,500 m3/day
- c. Waste water 4,750 m3/day
- d. Solid waste 92,000 kg/day
- e. Chilled water 24,000 GPM
- f. Fuel 27,000 bbls/day
Power Distribution system
Water Distribution system
- Capacity 13,600 m3/day
- Total capacity 24,000 m3
- Gross floor area 1,080 m2
- Major Equipment
- i. Fire pumps 7 ea. 0 1,020 m3/Jr.
- ii. Potable water pumps 4 ea. 0 227 m3/day
- i. Supply system 9,000 m
- ii. Control system 28,000 m
Waste Water System
- Capacity 6,000 m3/day
- Aircraft sanitary waste facility
- Capacity 75 m3/day
- Gross floor area 75 m3
- Aircraft wash water facility
- Capacity 47 m3/day
- Gross floor area 110 m3
- i. No. of lift stations 7 ea.
- ii. Gravity sewer pipe length 18,000 m
- iii. Force mains pipe length 16,500 m
- i. Gross floor area 120 m3
- ii. Digester capacity
- Total solids 1,520 kg/day
- Volatile solids 1,070 kg/day
- i. Central Plant 2,500 m.
- ii. Water treatment plant 2,600 m.
Irrigation system
- Capacity 435 m3/Hr.
- Gross floor area 310 m2
- Irrigation pumps 2 @ 230 m3/Hr.
- Tanks 2 @ 700 m3
Central Plant
Building
- Gross floor area 10,570 m2
Fuel System
- i. Jet fuel storage tanks 6 @ 6.7 x 10,000,000 L. ea.
- ii. Building (Gross floor areas)
- a. Pump house 1,340 m2
- b. Operating office/control building 500 m2
- c. Electrical equipment building 236 m2
- d. Foam concentrate building 88 m2
- i. Pipeline 16,000 m
- ii. Hydrants 44 ea.
- Administration staff for security
- Police and medical function 460 persons
- Gross floor area 12,110 m2
- Postal volume 16,000 Tons/year
- Gross floor area 14,460
- Gross floor area 3.240
- Requirements of meals 11,200 meals/day
- Gross floor area7,450 m2
- No. of sub-fire stations 2 ea.
- Gross floor area 1,420 m2 ea.
- Administration building 4,440 m2
- Maintenance building 6,600 m2
- Vehicle maintenance building 5,400 m2
- Warehouse 6,170 m2
Airlines Support Facilities
- Air Cargo Volume 176,000 tones/year
- Gross floor area 47,200 m2
- Meal volume 10,000 meal/day
- Gross floor area 17,300 m2
General Aviation Terminal
- Non-commercial passenger traffic 312,000 persons/year
- Gross floor area 5,210 m2
Community
- Capacity 36 beds
- Gross floor area 4,850 m2
- Gross floor area 930 m2
- Gross floor area 2,280 m2
- Gross floor area 550 m2
- Gross floor area 3,890 m2
- Gross floor area 780 m2
- Capacity 2,300 m3/day
- Gross floor area 1,930 m2
- Capacity 1,520 m3/fsy
- Gross floor area 2,100 m2
- Gross floor area 1,095 m2
West Terminal and Concourse
- Total 293,860 m2
- Service level 52,530 m2
- Arrival level 70,880 m2
- Boarding level 63,390 m2
- Mezzanine level 33,160 m2
- Penthouse 4,770 m2
- Contact gates 24 ea.
- (with 9 ea. Optional)
- Remote gates 7 ea.
- Number of bridges 31 ea.
- (with 10 ea. Optional)
- Moving walks 16 ea.
- (with 4 ea. ptional)
- Elevators 35 ea.
Escalators 43 ea.
- (with 9 ea. Optional)
- Departures 21 ea.
- Arrivals 21 ea.
- Domestic 2 ea.
- International 7 ea.
Mosque
- Capacity 2,000 persons
- Gross floor area 3,940
- Gross area 46,280m2
Royal Terminal
- Elevators 5 ea.
- Escalator 4 ea.
- Contact gates 2 ea.
- Ceremonial gate 1 ea.
Control Tower and ATS Building
- Gross floor area 840 m2
- Height 85.6 m
- Elevator 1 ea.
- Gross floor area 5,750 m2
Parking Garage
- Number of levels 3
- Gross floor area 178,700 m2
- Parking capacity 4,650 autos
- Elevators 12 ea.
Telecommunication and Meteorological System
Monitoring and Control System
- Fire and life safety
- Power supervisory
- HVAC and energy management
- Aircraft Fuel
- Airport water
- Airfield lighting
Security System
|